Connaught Utility Servicing Project Updates 2021

Posted on: October 22, 2021

Connaught Utility Servicing Project Update #10 - October 22, 2021

2021-10-07 Paving on Pine Photo

We are now in the final stages of the Connaught Utility Servicing Project. The next few weeks will be very busy with multiple crews on-site completing underground water and sewer mains and constructing the roadways prior to installation of concrete sidewalks and pavement. Things will be changing quickly, and we will do our best to communicate the changes on social media with as much notice as possible. On-site communications will remain clear and concise.

Plans for next week: 

  • Water and sanitary sewer to be completed by Monday, October 25 
  • Road Closure of Patricia Street from Spruce Ave to Pine Ave from Friday, October 22 to Monday, October 25 for the installation of a new fire hydrant at the intersection of Pine Ave. Residents are asked to use Geikie Street or Connaught Drive as detour routes. 
  • Roadway construction and grading on Connaught Drive started this week and will continue for the next few weeks 
  • Paving of Connaught Drive is scheduled to start Monday, November 8

Please note that these dates are tentative and are subject to change depending on the weather and unforeseen circumstances that occur during construction. We appreciate your continued patience and understanding, and thank you again for your feedback. For any questions, concerns or general feedback on this project please email capitalprojects@town.jasper.ab.ca or call 780-852-6501.