Connaught Utility Servicing Project Updates 2021

Posted on: November 5, 2021

Connaught Utility Servicing Project Update #12 - November 5, 2021

JCOS Concrete Pour

Crews continue to focus on concrete and paving work in order to wrap up the project for winter. 

The following is a list of project tasks and dates: 

  • Spruce Avenue, including the Patricia Street intersection, will be closed until November 11 to allow for roadway grading and paving. 
  • Spruce Avenue at the Connaught Drive intersection will be closed from November 5 to 12 for road construction and paving. A detour will be in place via Geikie Street or Sleepy Hollow Road. 
  • Paving of Connaught Drive will start (tentatively) on November 12.

Please note that these dates are tentative and are subject to change depending on the weather and unforeseen circumstances that occur during construction. 

We appreciate your continued patience and understanding, and thank you again for your feedback. For any questions, concerns or general feedback on this project please email capitalprojects@town.jasper.ab.ca or call 780-852-6501.


JCOS Concrete Sidewalks

JCOS Connaught Pre-pave

JCOS Concrete Pour