Connaught Utility Servicing Project Updates 2021

Posted on: November 12, 2021

Connaught Utility Servicing Project Update #13 - November 12, 2021

JCOS Concrete Pour

Paving work will start today (Friday) and continue through to early next week, which is when the project is expected to wrap up for the winter. 

  • Concrete work was completed on Tuesday.
  •  Paving of Connaught will start today (Friday) and will continue through the weekend and early next week. Connaught is expected to be fully open on Wednesday, November 17.
  • Paving of Pine Ave is expected to start on Wednesday, once Connaught is complete.
  • Once paving is complete GS Construction will be doing a final clean up and this project will be complete for the winter. There are a few more items that will need to be completed in the spring, which we will share in the next few weeks.

    We appreciate your continued patience and understanding throughout this project, and thank you again for your feedback. For any questions, concerns or general feedback on this project please email capitalprojects@town.jasper.ab.ca or call 780-852-6501.